File #: 20-0184    Name: Reject Bids for Contract 19-18-CD, Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities, CDBG 18291 & 18091
In control: Public Works & Planning
On agenda: 3/24/2020 Final action: 3/24/2020
Enactment date: Enactment #:
Title: Reject all bids for Contract 19-18-CD, Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities, Community Development Block Grant Project No. 18291 and 18091.
Attachments: 1. Agenda Item, 2. Location Maps

DATE:                     March 24, 2020

 

TO:                     Board of Supervisors

 

SUBMITTED BY:                     Steven E. White, Director

                     Department of Public Works and Planning

 

SUBJECT:                     Reject Bids for Contract No. 19-18-CD, Wastewater Treatment at the El Porvenir and Cantua Creek Facilities

 

RECOMMENDED ACTION(S):

TITLE

Reject all bids for Contract 19-18-CD, Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities, Community Development Block Grant Project No. 18291 and 18091.

REPORT

Approval of the recommended action will reject the bid received for the proposed Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities project (Project).  These facilities serve County Service Area Nos. 30 (El Porvenir) and 32 (Cantua Creek).  The Community Development Block Grant (CDBG) program made funding available for the Project, but it is an insufficient amount to cover the bid.  This item pertains to locations in District 1.

 

ALTERNATIVE ACTION(S):

 

There is no viable alternative action, as the allocated CDBG funding does not provide sufficient funds to construct the improvements, based on the bid. 

 

FISCAL IMPACT:

 

There is no increase in Net County Cost associated with the recommended actions.  All costs incurred for the Project were funded through the CDBG program.

 

DISCUSSION:

 

The planned work for the Project consists of adding headworks, replacing the aeration systems, and installing a flow metering system at each of the wastewater treatment plants.  Additionally, at El Porvenir, the pond liner requires repair and the levee adjacent to the aeration pond will need to be regraded.

 

On June 5, 2018, the Board approved $500,000 for the Project ($250,000 for each facility), as part of the 2018-19 Action Plan using CDBG funds, which is not enough to cover the amount of the bid received.

 

On January 21, 2020, the Department issued a Notice to Bidders for the Project, using the Department’s standard instructions and construction contract template.  On February 20, 2020, the Department held a bid opening and one bid was received.  W.M. Lyles bid was $691,257, which is $334,957, or 94%, higher than the engineer’s estimate of $356,300.

 

Plans and specifications for the Project were prepared by the Department’s Design Division.  Upon your Board’s rejection of the bid received, the Department will re-advertise for bids.  Under the Public Contract Code, no other option is available at this time. Upon holding a second bid opening, anticipated for April 23, the Department will return to your Board with the results.  Although not ideal, the slight delay associated with rebidding the project will not cause the project to miss funding deadlines, nor will it negatively impact the health and safety of the community.

 

ATTACHMENTS INCLUDED AND/OR ON FILE:

 

Location Maps

 

CAO ANALYST:

 

Sonia M. De La Rosa