Approve and authorize the Chairman to execute First Amendment to Agreement No. 13-623 with Biggs Cardosa Associates, Inc., for engineering consultant services related to the Travers Creek Bridge Replacement Project on Manning Avenue, Federal Project No. BRLS-5942(198) extending the maximum term by five years (three-year base contract with two optional one-year renewals) from October 8, 2018 to October 8, 2023, with no increase in the maximum amount of $566,372.
Attachments: 1. Agenda Item, 2. Location Map, 3. Agreement A-13-623-1 with Biggs Cardosa Assoc., Inc.

DATE:                     September 25, 2018

 

TO:                     Board of Supervisors

 

SUBMITTED BY:                     Steven E. White, Director

                     Department of Public Works and Planning

 

SUBJECT:                     Amendment to Agreement with Biggs Cardosa Associates, Inc.

 

RECOMMENDED ACTION(S):

TITLE

Approve and authorize the Chairman to execute First Amendment to Agreement No. 13-623 with Biggs Cardosa Associates, Inc., for engineering consultant services related to the Travers Creek Bridge Replacement Project on Manning Avenue, Federal Project No. BRLS-5942(198) extending the maximum term by five years (three-year base contract with two optional one-year renewals) from October 8, 2018 to October 8, 2023, with no increase in the maximum amount of $566,372.

REPORT

Approval of the recommended action will extend the performance period of the agreement for an additional maximum five-year term to allow the consultant to complete the design and provide technical expertise during construction. On October 8, 2013, Biggs Cardosa Associates, Inc., was selected as the most qualified design engineering consultant following a Request for Proposal process.  The extension is due to a lengthy right-of-way acquisition phase.  This item pertains to a location in District 4. 

 

ALTERNATIVE ACTION(S):

 

If the recommended action is not approved, the agreement will expire by its terms on October 8, 2018, and the project will be delayed, potentially jeopardizing Federal funds. In addition, selecting a different consultant would not be feasible, as continuity of design of the project would be impacted.

 

FISCAL IMPACT:

 

There is no increase in Net County Cost associated with the recommended action.  The Federal Highway Bridge Program provides up to 88.53% or $501,409 of Biggs Cardosa’s fee for the Travers Creek Bridge Replacement Project on Manning Avenue.  The local match (approximately 11.47% or $64,963) will be paid out of Road Fund 0010.  Sufficient appropriations and estimated revenues for the project are included in the Department of Public Works and Planning - Roads Org 4510 FY 2018-19 Adopted Budget.

 

DISCUSSION:

 

The proposed project consists of replacing the structurally deficient Travers Creek Bridge on Manning Avenue, approximately one half mile west of Alta Avenue, approximately one mile east of the city limits of the City of Reedley, with a new bridge that meets current standards. 

 

On October 8, 2013, the Board approved Agreement No. 13-623 with Biggs Cardosa Associates, Inc. to perform design engineering for the project for a three-year term with two-optional one-year renewals.  The five-year term was not of sufficient length, as the consultant agreement needs to be in effect through completion of construction, estimated in 2021.  The amendment will extend the term of the agreement for an additional three years with two optional one-year renewals in the event that construction goes beyond 2021. 

 

With your Board’s approval, the agreement with Biggs Cardosa will be extended through October 8, 2023.

 

OTHER REVIEWING AGENCIES:

 

California Department of Transportation provides oversight on local transportation projects where Federal funds are allocated.

 

REFERENCE MATERIAL:

 

BAI #39, October 8, 2013

 

ATTACHMENTS INCLUDED AND/OR ON FILE:

 

Location Map

On file with Clerk - Amendment to Agreement No. 13-623 with Biggs Cardosa Associates, Inc.

 

CAO ANALYST:

 

Sonia M. De La Rosa