Recommended Action(s)
1. Approve and authorize the Chairman to execute Program Supplement No. N223 Rev. 1 Master Agreement for Federal Aid No. 06-5942R with the California Department of Transportation for Fowler Avenue from South Avenue to Elkhorn Avenue, Federal Project No. CML-5942(211), ($3,825,362). 2. Approve and authorize the Chairman to execute Program Supplement No. N259 Rev. 1 Master Agreement for Federal Aid No. 06-5942R with the California Department of Transportation for Kamm Avenue from SR 145 to Jameson Avenue, Federal Project No. CML-5942(254), ($2,858,215).
Attachments: 1. Agenda Item, 2. Location Maps, 3. Agreement A-17-470 Program Supplement N223, 4. Agreement A-17-471 Program Supplement Agreement N259

DATE:                     September 12, 2017

 

TO:                     Board of Supervisors

 

SUBMITTED BY:                     Steven E. White, Director

Department of Public Works and Planning

 

SUBJECT:                     Program Supplement Agreements for Fowler Avenue from South Avenue to Elkhorn Avenue and Kamm Avenue from SR 145 to Jameson Avenue Shoulder Improvement Projects

 

RECOMMENDED ACTION(S):

TITLE

1.                     Approve and authorize the Chairman to execute Program Supplement No. N223 Rev. 1 Master Agreement for Federal Aid No. 06-5942R with the California Department of Transportation for Fowler Avenue from South Avenue to Elkhorn Avenue, Federal Project No. CML-5942(211), ($3,825,362).

 

2.                     Approve and authorize the Chairman to execute Program Supplement No. N259 Rev. 1 Master Agreement for Federal Aid No. 06-5942R with the California Department of Transportation for Kamm Avenue from SR 145 to Jameson Avenue, Federal Project No. CML-5942(254), ($2,858,215).

REPORT

The recommended actions will authorize the Chairman to execute Program Supplement Agreements with the California Department of Transportation (Caltrans) to allow reimbursement of project costs with Federal funds.

 

ALTERNATIVE ACTION(S):

 

Not approving the recommended actions will result in de-obligation of the allocated Federal funding and the return of any funds reimbursed to the County.

 

FISCAL IMPACT:

 

There is no Net County Cost associated with the recommended actions.

 

The first recommend action is divided into two parts of funding. The Federal funds will provide up to $3,825,362 for the Preliminary Engineering, Right-of-Way, and Construction phases of the shoulder improvements on Fowler Avenue from South Avenue to Elkhorn Project. The County’s local match for the shoulder improvements is estimated to be $254,446. The construction cost for the asphalt concrete overlays is estimated to be $2,063,155 for a total of $2,317,601 and will be paid out of the Road Fund. Sufficient appropriations have been and will be included in the Public Works and Planning - Road Org 4510 Budgets for prior, current, and future fiscal years.

 

The second recommend action will provide Federal funds up to $2,858,215 for the Preliminary Engineering and construction phases of the Kamm Avenue for SR 145 to Jameson Avenue project. A local match of $713,461 will be paid out of the Road Fund. Sufficient appropriations have been and will be included in the Public Works and Planning - Road Org 4510 Budgets for prior, current, and future fiscal years.

 

DISCUSSION:

 

The purpose of the Congestion Mitigation and Air Quality (CMAQ) Program is to fund transportation projects that will contribute attainment or maintenance of the National Ambient Air Quality Standard for ozone, carbon monoxide, and particulate matter.

 

Recommended Action #1:

This CMAQ project consists of adding 8 feet of new paved shoulder to each side of Fowler Avenue from Elkhorn Avenue to South Avenue, a distance of approximately 9.0 miles. The project also includes a County-only funded portion that includes an asphalt concrete overlay, which consists of placing hot mix asphalt and centerline striping on the existing 24 foot wide travel way.  The project began in FY 2011-12 with initial design work. Construction is expected to begin March 2018 with the completion anticipated June 2018.

 

Recommended Action #2:

This CMAQ project consists of adding approximately 4 feet of new paved shoulder to each side of Kamm Avenue from SR 145 to Jameson Avenue, a distance of 6.02 miles. This will widen the existing 24-foot wide roadway to consist of two 12-foot wide travel lanes with four-foot wide paved shoulders on each side of the roadway.  The project began in FY 2014-15 with initial design work. Construction is expected to begin March 2018 with the completion anticipated June 2018.

 

OTHER REVIEWING AGENCIES:

 

Caltrans prepared the Program Supplement Agreements.

 

REFERENCE MATERIAL:

 

BAI #55, March 13, 2007

BAI #66, May 22, 2012

BAI #72, July 14, 2015

 

ATTACHMENTS INCLUDED AND/OR ON FILE:

 

Location Maps

On file with Clerk - Program Supplement Agreements N223 and N253

 

CAO ANALYST:

 

John Hays