DATE: February 6, 2024
TO: Board of Supervisors
SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning
SUBJECT: Award Class A and Class B Job Order Contracts
RECOMMENDED ACTION(S):
TITLE
1. Adopt specifications for Contract Nos. 23-19-J, 23-20-J, 23-21-J, 23-22-J, and 23-25-J Class A (General Engineering) Job Order Contracts; and
2. Find that Papich Construction, 398 Sunrise Terrace, Arroyo Grande, CA 93420, is the lowest bidder for Contract No. 23-19-J, and that the deviation from strict bidding requirements is immaterial and is hereby waived, at the discretion of the Board and in furtherance of the best interests of the County; and
3. Award Contract No. 23-20-J to the bidder with the second lowest bid, Avison Construction, 40434 Brickyard Dr., Madera, CA 93636, total not to exceed $5,797,725; and
4. Award Contract No. 23-21-J to the bidder with the third lowest bid, Terra West Construction, 1030 Gettysburg Avenue, Suite 107 Clovis, CA 93612, total not to exceed $5,797,725; and
5. Award Contract No. 23-22-J to the bidder with the fourth lowest bid, Yarbs Grading and Paving, 11339 S. Peach Avenue, Fresno CA 93725, total not to exceed $5,797,725; and
6. Find that Teichert Construction, 400 Sunrise Avenue, Suite 300, Roseville, CA 93661, is the fifth lowest bidder for Contract No. 23-25-J, and that the deviation from strict bidding requirements is immaterial and is hereby waived, at the discretion of the Board and in furtherance of the best interests of the County; and
7. Adopt specifications for Contract Nos. 23-J-05, 23-J-06, 23-J-07, and 23-J-08 Class B (General Building) Job Order Contracts; and
8. Award Contract No. 23-J-05 to the bidder with the lowest bid, Exbon Development, 13831 Newhope Street, Garden Grove, CA 92843, total not to exceed $5,797,725; and
9. Award Contract No. 23-J-06 to the bidder with the second lowest bid, Puma Construction, 4387 W Santa Ana, Fresno, CA 93722, total not to exceed $5,797,725; and
10. ...