DATE: January 21, 2020
TO: Board of Supervisors
SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning
SUBJECT: Agreements for the Laton Sidewalk Project, Federal Project No. HSIPL-5942(275)
RECOMMENDED ACTION(S):
TITLE
1. Adopt resolution assuming financial responsibility for costs of relocation of Laton Community Services District's water and wastewater facilities required for Laton Sidewalk Project, Federal Project No. HSIPL-5942(275);
2. Approve and authorize the Director of the Department of Public Works and Planning, subject to the review and approval of County Counsel as to legal form and the Auditor-Controller/Treasurer-Tax Collector as to accounting form, to execute a Utility Agreement with Laton Community Services District, and any amendments thereto, in connection with the construction of the Laton Sidewalk Project;
3. Approve and authorize the Director of the Department of Public Works and Planning, subject to the review and approval of County Counsel as to legal form and the Auditor-Controller/Treasurer-Tax Collector as to accounting form, to execute a Utility Agreement with Laguna Irrigation District, and any amendments thereto, in connection with the construction of the Laton Sidewalk Project;
4. Accept the as-is donation of a storm drainage basin area (at Gonser Street and East Riverdale Avenue in Laton) and connected storm water drainage improvements along Gonser Street in Laton from the Laton CSD, and approve and authorize the Director to approve and execute a related Agreement (to acquire property and right of way and to assume certain storm drain-related operations and maintenance duties), with Laton CSD in substantial form as the attached Agreement, on file with the Clerk, including any revisions thereto as may be approved by the Director as he deems to be in the best interest of the County, all of which shall be subject to the review and approval of County Counsel as to legal form and the Auditor-Controller/...