File #: 18-0611    Name: Program Supplement Agreement N252 Rev.1
In control: Public Works & Planning
On agenda: 8/7/2018 Final action: 8/7/2018
Enactment date: Enactment #: Agreement No. 18-430
Title: Approve and authorize Chairman to execute Program Supplement Agreement No. N252 Rev. 1 to Administering Agency-State Master Agreement for Federal Aid Project No. 06-5942R with California Department of Transportation for Federal Project No. BRLO-5942(238) Ennis Road over Sand Creek Bridge ($100,000).
Attachments: 1. Agenda Item, 2. Location Map, 3. Agreement A-18-430 Program Supplement Agreement N252 Rev.1
DATE: August 7, 2018

TO: Board of Supervisors

SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning

SUBJECT: Program Supplement Agreement No. N252 Rev. 1

RECOMMENDED ACTION(S):
TITLE
Approve and authorize Chairman to execute Program Supplement Agreement No. N252 Rev. 1 to Administering Agency-State Master Agreement for Federal Aid Project No. 06-5942R with California Department of Transportation for Federal Project No. BRLO-5942(238) Ennis Road over Sand Creek Bridge ($100,000).
REPORT
Approval of the recommended action would authorize the Chairman to execute a Program Supplement Agreement (PSA) with the California Department of Transportation (Caltrans) to allow reimbursement of project costs with Federal funds. The project consists of replacement of the existing Sand Creek Bridge to meet current standards. The bridge is located on Ennis Road, 0.3 miles south of George Smith Road. The PSA will provide funding for the project's right-of-way phase. This item pertains to a location in District 5.

ALTERNATIVE ACTION(S):

There is no viable alternative action. If your Board does not approve the recommended agreement, it will result in de-obligation of the allocated funding.

FISCAL IMPACT:

There is no Net County Cost associated with the recommended action. The estimated total cost for the project is $480,000. Approval of the recommended action will provide $100,000 for right-of-way phase. On October 28, 2018, your Board approved $40,000 for the preliminary engineering phase. Caltrans later approved the amendment modification to add $340,000 for the total of $380,000. The PSA will allow for 100% cost reimbursement up to $480,000 from the Federal Highway Bridge Program (HBP) along with toll credits. Sufficient appropriations and estimated revenues will be included in the Department of Public Works and Planning - Roads Org 4510 FY 2018-19 Recommended Budget. Upon completion of the right-of-way phase, additional funds will b...

Click here for full text