File #: 19-0205    Name: Declaration of Projects to be Performed by Force Account
In control: Public Works & Planning
On agenda: 3/12/2019 Final action: 3/12/2019
Enactment date: Enactment #:
Title: Declare the FY 2018-19 Anticipated Day Labor Overlay Road Segment projects identified on Exhibit A are intended to be performed by force account in accordance with California Public Contract Code, section 22031(g).
Attachments: 1. Agenda Item, 2. Exhibit A
DATE: March 12, 2019

TO: Board of Supervisors

SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning

SUBJECT: Declaration of FY 2018-19 Anticipated Projects to be Performed by Force Account

RECOMMENDED ACTION(S):
TITLE
Declare the FY 2018-19 Anticipated Day Labor Overlay Road Segment projects identified on Exhibit A are intended to be performed by force account in accordance with California Public Contract Code, section 22031(g).
REPORT
Approval of the recommended action will allow the Department of Public Works and Planning to comply with California Public Contract Code (CPCC), section 22031(g), which limits the amount of new construction and reconstruction that can be done by county forces. The section also requires projects intended to be performed by force account to be declared by the Board of Supervisors or the County Road Commissioner each fiscal year. This item pertains to Districts 1, 4, and 5.

ALTERNATIVE ACTION(S):

If the recommended action is not approved, county forces will be unable to perform some of the anticipated maintenance and reconstruction projects identified in Exhibit A by force account. This will require Department staff to bid out additional maintenance and construction projects, causing delays in delivery of the service and resulting in additional project costs.

FISCAL IMPACT:

There is no Net County cost associated with the recommended action. Funds for anticipated day labor overlay road segment projects by county forces are included in the Department - Roads' Org 4510 FY 2018-19 Adopted Budget.

DISCUSSION:

CPCC, section 22031(g) was amended on September 2014 with the passage of Assembly Bill 2752 (Chapter 345, Statutes of 2014). The section limits the amount of new construction and reconstruction that can be done by county forces to 30% of the total value of all work performed by force account other than maintenance as reported in the Controller's Streets and Roads Annual report as of March 1...

Click here for full text