DATE: October 8, 2019

TO: Board of Supervisors

SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning

SUBJECT: Agreement with the Caruthers Community Services District
(CDBG 19111)

RECOMMENDED ACTION(S):
TITLE
Approve and authorize the Chairman to execute Agreement with the Caruthers Community Services District for the Caruthers Lift Station Replacement, Community Development Block Grant Project No. 19111, effective upon execution through April 30, 2021 ($250,000).
REPORT
Approval of the recommended action will provide Community Development Block Grant (CDBG) funding for the Caruthers Lift Station Replacement Project (Project), included in the County's 2019-20 Action Plan approved by your Board on June 4, 2019. The Project cost is estimated at $250,000, and consists of rehabilitating a sanitary sewer lift station located on the south corner of Tahoe Avenue and Pear Street in the unincorporated community of Caruthers. If necessary to complete the Project by April 30, 2021, the Caruthers Community Services District ( District) will provide a local financial contribution is excess of the CDBG funds. This item pertains to a location in District 4.

ALTERNATIVE ACTION(S):

Your Board may reject the Project, amend the 2019-20 Action Plan to modify or delete the Project, and direct staff to identify another project from the 2019-20 Back-Up list for consideration. However, deletion may impact the County's ability to meet its CDBG expenditure timelines set by the U.S. Department of Housing and Urban Development (HUD).

FISCAL IMPACT:

There is no Net County Cost associated with the recommended action. The total estimated Project cost is $250,000. CDBG funds in the amount of $250,000 from the County's unincorporated area allocation are included in the Department of Public Works and Planning - CDBG Org 7205 FY 2019-20 Adopted Budget. The County provides the funds on a reimbursement basis. The District will provide a local financial con...