File #: 16-1252    Name: Right-of-Way Acquisition - American Avenue - SH99 to Temperance Avenue
In control: Public Works & Planning
On agenda: 10/18/2016 Final action: 10/18/2016
Enactment date: Enactment #:
Title: Accept the easement deed and authorize the Chairman to execute the right-of-way contract required for the American Avenue from SR99 to Temperance Avenue Road Improvement Project for a total monetary consideration of $3,400.
Attachments: 1. Agenda Item, 2. Exhibit A, 3. Location Map, 4. Right-of-Way Contract, 5. Grant of Easement

DATE:                     October 18, 2016

 

TO:                     Board of Supervisors

 

SUBMITTED BY:                     Steven E. White, Director

Department of Public Works and Planning

 

SUBJECT:                     Right-of-Way Acquisition for the American Avenue from SR99 to Temperance Avenue Road Improvement Project - Federal Project No. HPLUL 5942(171) and (172)

 

RECOMMENDED ACTION(S):

TITLE

Accept the easement deed and authorize the Chairman to execute the right-of-way contract required for the American Avenue from SR99 to Temperance Avenue Road Improvement Project for a total monetary consideration of $3,400.

REPORT

Approval of the recommended action will authorize the purchase of additional right-of-way on American Avenue at a cost of $3,400 (shown on Exhibit A, attached).  This acquisition will facilitate the American Avenue from SR99 to Temperance Avenue Road Improvement Project. 

 

ALTERNATIVE ACTION(S):

 

The Board may reject the purchase of this right-of-way.  This would prevent the County from obtaining the necessary right-of-way to proceed with the project.  If the necessary right-of-way is not acquired, the project will be cancelled and funds received for the project would have to be returned to the Federal Highway Administration. 

 

FISCAL IMPACT:

 

There will be no Net County Cost associated with the recommended action.  A warrant or check will be drawn on the Road Fund 0010, made payable to the individual grantors listed below.  This project is eligible for 80% reimbursement under the Federal High Priority Project Demonstration program.  The remaining 20% will be paid out of the Road Fund.  Sufficient appropriations for this project are included in the FY 2016-17 Public Works and Planning - Roads Org 4510 Adopted Budget. 

 

The property owner names, address and the basis of the compensation associated with this parcel is as follows: Parcel 9 - Jasbir Singh and Jaswinder Kaur, Trustees, 3564 E. Belmont Avenue, Fresno, CA  93702 - 0.014 acre road easement, four (4) pots/risers and flood irrigation line.

 

Of the total compensation provided pursuant to this agenda Item, all $3,400 is for a permanent roadway easement.

 

DISCUSSION:

 

The proposed project involves the reconstruction of approximately 1.4 miles of American Avenue, from the eastern right-of-way of SR99 to Clovis Avenue, and the placement of an asphalt concrete overlay over 2 miles from Clovis Avenue to 100 feet east of Temperance Avenue. 

 

The scope of work also includes the realignment and signalization of the currently-substandard intersection of American Avenue and Golden State Boulevard.  New railroad crossing guards and lights will also be installed.

 

It is anticipated that construction may commence in the spring of 2018.

 

REFERENCE MATERIAL:

 

BAI #61, December 10, 2013

BAI #55, June 21, 2016

 

ATTACHMENTS INCLUDED AND/OR ON FILE:

 

Exhibit A

Location Map

On file with Clerk - Right-of-Way Contract

On file with Clerk - Grant of Easement

 

CAO ANALYST:

 

John Hays