DATE:                     July 7, 2020

 

TO:                     Board of Supervisors

 

SUBMITTED BY:                     Steven E. White, Director

                     Department of Public Works and Planning

 

SUBJECT:                     Award Contract No. 19-09-C, Fresno Canal on McKinley Avenue Bridge Replacement Project

 

RECOMMENDED ACTION(S):

TITLE

Adopt plans and specifications and award Contract 19-09-C, Fresno Canal on McKinley Avenue Bridge Replacement Project, Federal Project No. BRLS-5942(225) to the low bidder, Agee Construction Corporation, PO Box 629, Clovis, CA 93613, in the amount of $1,489,728.

REPORT

Approval of the recommended action will award a Federally funded Highway Bridge Program (HPB) bridge replacement project.  This item pertains to a location in District 3.

 

ALTERNATIVE ACTION(S):

 

If the recommended action is not approved, the bridge replacement will be delayed.

 

FISCAL IMPACT:

 

There is no increase in Net County Cost associated with the recommended actions.  The maximum anticipated construction cost is $1,576,714 based on the low bid and including the Director’s allowance for change orders of $86,986.  The bridge replacement is 100% Federally funded through the HBP.  Sufficient appropriations and estimated revenues will be included in the Department’s Road Fund Org 4510 FY 2020-21 Proposed Budget.

 

DISCUSSION:

 

The work to be done consists, in general of removing and replacing the existing timber 48-foot long and 24-foot wide Fresno Canal Bridge on McKinley Avenue with a new single span bridge 61 feet long and 32 feet wide to meet current standards.  The existing structure was constructed in 1940 and had a 6-inch concrete deck added in 1970.  The new bridge will be located along the same road alignment with a slightly higher profile.  The project also includes reconstruction of the approach roadways. Canal access roads will be realigned around new crash cushions at each corner of the bridge.  Full street closure is required during construction and a detour will be provided.

 

The project was advertised on May 5, 2020, and the bid opening was held on June 12, 2020. Five bids were received.  Agee Construction’s bid was $1,489,728, which is $228,902, or 13.32%, lower than the engineer’s estimate of $1,718,630.

 

The bidders, their respective bids, and Disadvantaged Business Enterprise (DBE) goals are shown below.  As a federally funded project, there was a DBE goal of 15%.

 

Bidder                                 Bid                     DBE Commitment

Agee Construction             $1,489,728.00                30%

American Paving                $1,720,630.50                15%

Dawson-Mauldin                $1,722,722.50                 0%

Viking Construction            $1,842,780.00                N/A

Bush Engineering               $2,728,586.46                N/A

 

Plans and specifications were prepared by the Department’s structural engineering consultant, TRC Engineers and are on file with the Department.  It is anticipated that construction will begin in September 2020 and will be completed in April 2021.

 

ATTACHMENTS INCLUDED AND/OR ON FILE:

 

Location Map

Site Plan

 

REFERENCE MATERIAL:

 

BAI #45, April 17, 2018

BAI #49, May 16, 2017

BAI #49, December 13, 2016

BAI #50, December 13, 2016

BAI #34, September 17, 2013

 

CAO ANALYST:

 

Debbie Paolinelli