Fresno County CA header
 
File #: 21-0584    Name: Change Order Contract 19-18-CD
In control: Public Works & Planning
On agenda: 7/13/2021 Final action: 7/13/2021
Enactment date: Enactment #:
Title: 1. Approve an increase in Community Development Block Grant funds provided for the El Porvenir and the Cantua Creek Wastewater Treatment Plant Improvements, Community Development Block Grant Project Nos. 18291 and 18091, increasing the maximum funds provided for these projects by $33,000; to $933,000; and 2. Authorize the Chairman to execute a Contract Change Order for Contract No. 19-18-CD - Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities, which will increase the contract amount by $66,617.46, exceeding the authorized Director's limit of $44,537, increasing the maximum by $66,617.46 to a total of $707,265.46.
Attachments: 1. Agenda Item, 2. Location Map


DATE: July 13, 2021

TO: Board of Supervisors

SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning

SUBJECT: Contract Change Order for Contract 19-18-CD, Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities - Community Development Grant Block Grants #18291 and #18091

RECOMMENDED ACTION(S):
TITLE
1. Approve an increase in Community Development Block Grant funds provided for the El Porvenir and the Cantua Creek Wastewater Treatment Plant Improvements, Community Development Block Grant Project Nos. 18291 and 18091, increasing the maximum funds provided for these projects by $33,000; to $933,000; and
2. Authorize the Chairman to execute a Contract Change Order for Contract No. 19-18-CD - Wastewater Treatment Improvements at the El Porvenir and Cantua Creek Facilities, which will increase the contract amount by $66,617.46, exceeding the authorized Director's limit of $44,537, increasing the maximum by $66,617.46 to a total of $707,265.46.
REPORT
Approval of the recommended actions will provide an additional $33,000 in Community Development Block Grant (CDBG) funds to the Cantua Creek Wastewater Treatment Plant Project and will authorize the Chairman to execute contract changes necessary to authorize the proposed additional work, which exceeds the Director's limit for contract change orders and increases the total contract amount. This item pertains to a location in District 1.

ALTERNATIVE ACTION(S):

If the recommended actions are not approved, there will not be sufficient funds to perform the additional work. Therefore, the Department will complete construction of the project as previously approved and will not authorize the contractor to perform the additional work.

FISCAL IMPACT:

There is no increase in Net County Cost associated with the recommended actions. The project was awarded by the Board on July 7, 2020 and is funded by the CDBG Program. The first recommended action would increase the to...

Click here for full text