Fresno County CA header
 
File #: 18-1044    Name: Right-of-Way Acquisition Travers Creek Bridge Replacement - Manning Ave.
In control: Public Works & Planning
On agenda: 10/23/2018 Final action: 10/23/2018
Enactment date: Enactment #:
Title: Accept Easement Deeds and authorize the Chairman to execute the Right-of-Way Contracts, Permit to Enter for Leach Field Reconfiguration and Grade Match, Temporary Construction Permit, and Grade Match for Driveway Modification required to facilitate the Travers Creek Bridge Replacement on Manning Avenue, Federal Project No. BRLS-5942(198), for a total monetary consideration of $35,600.
Attachments: 1. Agenda Item, 2. Exhibit A, 3. Location Map, 4. Grants of Easement, 5. Right-of-Way Contracts, 6. Temporary Construction Permit, 7. Grade Match for Driveway Modification, 8. Permit to Enter for Leach Field Reconfiguration and Grade Match
DATE: October 23, 2018

TO: Board of Supervisors

SUBMITTED BY: Steven E. White, Director
Department of Public Works and Planning

SUBJECT: Right-of-Way Acquisition for Travers Creek Bridge Replacement Project on Manning Avenue - Federal Project No. BRLS-5942(198)

RECOMMENDED ACTION(S):
TITLE
Accept Easement Deeds and authorize the Chairman to execute the Right-of-Way Contracts, Permit to Enter for Leach Field Reconfiguration and Grade Match, Temporary Construction Permit, and Grade Match for Driveway Modification required to facilitate the Travers Creek Bridge Replacement on Manning Avenue, Federal Project No. BRLS-5942(198), for a total monetary consideration of $35,600.
REPORT
Approval of the recommended action will authorize the purchase of additional right-of-way required to facilitate the replacement of an existing structurally deficient two lane bridge on Manning Avenue as shown on Exhibit A. This item pertains to a location in District 4.

ALTERNATIVE ACTION(S):

Your Board may reject the purchase of this right-of-way; however, this would prevent the County from obtaining the necessary right-of-way to proceed with the project. If the necessary right-of-way is not acquired, the project will be cancelled and all funds received for the project would have to be returned to the Federal Highway Administration.

FISCAL IMPACT:

There is no Net County Cost associated with the recommended action. This project is eligible for reimbursement under the Federal Highway Bridge Program (HBP). The HBP program will provide 88.53% of funds for right-of-way acquisition for this project. The remaining 11.47% will be paid out of the Road Fund 0010. Two checks will be issued from the Road Fund payable to the individual grantor(s) listed below. Sufficient appropriations for this project are included in the Department of Public Works and Planning - Roads Org 4510 FY 2018-19 Adopted Budget.

Listed below are the owners, mailing addresses, amounts, and the basis of the comp...

Click here for full text